• High Court B

High Court B

We have recently completed our latest project for the Scottish Court and Tribunal Service, the refurbishment of High Court B in Glasgow.

This £850k project was completed within 17 weeks and consisted of:

  • Complete new M&E package including new AHU
  • Bespoke furniture in main Court area
  • New partitions, ceilings, doors and skirtings
  • Decoration
  • Soft flooring
  • PA, security intruder and fire alarms
  • Construction of new public toilets and witness rooms

Due to the success of this project we are currently in negotiations for the refurbishment contract for High Court A, which will commence on site the end of June.

2017-08-24T15:54:02+00:00